What is the primary goal of sprint planning in Adobe Workfront?

To review past sprint performance and outcomes

To define the work to be completed in the upcoming sprint and allocate resources accordingly

The primary goal of sprint planning in Adobe Workfront is to define the work to be completed in the upcoming sprint and allocate resources accordingly. This process sets the foundation for the sprint by identifying specific tasks and deliverables that need to be accomplished within a designated time frame. During sprint planning, the team typically assesses the backlog, selects user stories, and discusses their priorities.

By clarifying what needs to be done and assigning resources, the team enhances its focus and ensures that everyone understands the objectives for the upcoming sprint. This structured approach allows team members to align their efforts toward common goals, leading to more effective collaboration and a higher chance of achieving the desired outcomes.

The other choices do not accurately represent the main purpose of sprint planning. Reviewing past performance focuses on reflection rather than forward planning, while assessing team member skills and reassigning roles pertains more to team dynamics than to the specific objectives of a sprint. Celebrating completed tasks is important for morale and acknowledgment, but it does not contribute to the planning and preparation necessary for achieving future sprint goals.

Get further explanation with Examzify DeepDiveBeta

To assess team member skills and reassign roles

To celebrate completed tasks from the past sprint